Maintain operations
The cooling asset had to be replaced in coordination with an operating rendering facility, requiring careful staging around production, access and critical services.


Feature project
DeliveredIndustrial infrastructure
Remediating a critical cooling asset without interrupting the facility it serves.
Explore the projectProject overview
Stokes Rousseau was engaged to manage the remediation and replacement of an industrial cooling dam at a large operating facility. The project extended from early civil works and design management through major dam construction and delivery of the new pumphouse.
What had to be solved
The programme combined heavy civil works, controlled dredging and live-service coordination in an environmentally sensitive work zone.

The cooling asset had to be replaced in coordination with an operating rendering facility, requiring careful staging around production, access and critical services.
Surface water run-off, dam decommissioning and the removal of silt and biosolids all had to be managed under strict environmental controls.
Early civil works proceeded to a tight programme while Stokes Rousseau simultaneously led the design team through development of the new dam solution.

The Stokes response
Stokes Rousseau gave the client one point of coordination across design management, superintendent services and direct principal-contractor delivery.
Early civil works established heavy-haulage access and the surface-water controls needed for the main remediation programme.
The existing dam and pumphouse were taken out of service before dredging removed accumulated silt and biosolids through a carefully managed environmental process.
Stokes Rousseau acted as Superintendent for the major civil package and as Principal Contractor for the new pumphouse, aligning both streams with the live facility.
Outcome
The completed works provide a larger HDPE-lined dam, new civil infrastructure and a purpose-built pumphouse incorporating extensive electrical and hydraulic services, pumps and floating equipment. Delivery remained coordinated with the facility's ongoing operations throughout.
Project statusDelivered